The Efficiency of Project Planning in IT Service Provider Using Traditional Methods, and CPM
A Comparative Study
- DOI
- 10.2991/978-94-6463-008-4_144How to use a DOI?
- Keywords
- CPM; PERT; time efficiency; project management; information system
- Abstract
This research was conducted in an IT service provider that provides the installation of information systems for customers. Planned projects often did not meet their target set by both provider and customer. For example, an SAP project that was set to be completed in six months was delayed until two years by some problems in operational activities. So, the CPM methods were conducted to be used in this case to see the efficiency of meeting the target set previously. Generally, these methods are completed in steps such as identifying the scope and breaking it down into components activities; dependency logic settings and development project network; estimating the duration of each activity; identifying critical path, float, and completion time duration; and crashing stage in several activities needed. This will give a result of comparison between the traditional method delivered and the CPM method using units of time completion. The traditional method using a Bar Chart results in 150 days of project schedule and the CPM Method can be faster with 140 days of Project Schedule. The most efficient method will be proposed to be used in time-consuming projects in the future with the additional recommendation.
- Copyright
- © 2023 The Author(s)
- Open Access
- Open Access This chapter is licensed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons license and indicate if changes were made.
Cite this article
TY - CONF AU - Alexander Tan AU - Isfenti Sadalia AU - Rulianda Purnomo Wibowo PY - 2022 DA - 2022/12/05 TI - The Efficiency of Project Planning in IT Service Provider Using Traditional Methods, and CPM BT - Proceedings of the 19th International Symposium on Management (INSYMA 2022) PB - Atlantis Press SP - 1170 EP - 1176 SN - 2352-5428 UR - https://doi.org/10.2991/978-94-6463-008-4_144 DO - 10.2991/978-94-6463-008-4_144 ID - Tan2022 ER -