Research on the Treatment Plan for Anchor Ropes in the Construction of Subway Bored Pile
- DOI
- 10.2991/978-94-6463-556-0_14How to use a DOI?
- Keywords
- subway station drilling and grouting pile anchor cable treatment plan; reference significance
- Abstract
This study primarily explores treatment solutions for anchor cables encountered during the construction of subway bored piles. As pile anchor forms become prevalent in foundation pit support for high-rise buildings, the intersection of subway lines with existing anchor cable areas poses considerable challenges. The study aims to develop practical and feasible anchor cable treatment plans to facilitate efficient, economical, and safe completion of subway station and other open-cut retaining structures. Taking the Youyi South Street Station of Shijiazhuang Metro Line 4 as an example, through comparative analysis of different treatment schemes, the optimal approach is identified, providing valuable references for similar engineering projects.
- Copyright
- © 2024 The Author(s)
- Open Access
- Open Access This chapter is licensed under the terms of the Creative Commons Attribution-NonCommercial 4.0 International License (http://creativecommons.org/licenses/by-nc/4.0/), which permits any noncommercial use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons license and indicate if changes were made.
Cite this article
TY - CONF AU - Shuanding Liu AU - Jinchang Zhang AU - Bo Zhang AU - Zengxin Li PY - 2024 DA - 2024/10/29 TI - Research on the Treatment Plan for Anchor Ropes in the Construction of Subway Bored Pile BT - Proceedings of the 2024 6th International Conference on Structural Seismic and Civil Engineering Research (ICSSCER 2024) PB - Atlantis Press SP - 115 EP - 121 SN - 2352-5401 UR - https://doi.org/10.2991/978-94-6463-556-0_14 DO - 10.2991/978-94-6463-556-0_14 ID - Liu2024 ER -