Proceedings of the Widyatama International Conference on Engineering 2024 (WICOENG 2024)

Identification of Standard Times to Determine Production Capacity: A Case Study

Authors
Sabiqul C. R. Ramadhan1, Verani Hartati1, *
1Industrial Engineering Department, Widyatama University, Bandung, Indonesia
*Corresponding author. Email: verani.hartati@widyatama.ac.id
Corresponding Author
Verani Hartati
Available Online 29 December 2024.
DOI
10.2991/978-94-6463-618-5_20How to use a DOI?
Keywords
standard times; production capacity; time study
Abstract

PT XYZ is one of the companies in Bandung engaged in the textile industry. The company’s principal product is a plain T-shirt. The issue at PT XYZ is that the production capacity of plain T-shirts is not clearly defined, resulting in inconsistency and inaccuracy in production time. This, in turn, leads to delivery times that do not align with the agreed customer expectations. This research employs a quantitative methodology with a time study approach, to calculate the standard time, determine the production capacity of plain T-shirts, and formulate recommendations to enhance production capacity. The total standard time for each production process can be identified. The standard time is divided by the number of operators, resulting in the system cycle time. The system cycle time for the production of plain T-shirt A allows for the calculation of a capacity of 86 units per hour, while plain T-shirt B has a capacity of 101 units per hour. The research findings indicate that the total standard time required to produce one unit of plain T-shirt A is 398,54 s, and 412,63 s for plain T-shirt B. The production capacity of plain T-shirt A is 689 units per day, while that of plain T-shirt B is 810 units per day. Recommendations to increase capacity can be made in two ways: by adding operators or by increasing working hours.

Copyright
© 2024 The Author(s)
Open Access
Open Access This chapter is licensed under the terms of the Creative Commons Attribution-NonCommercial 4.0 International License (http://creativecommons.org/licenses/by-nc/4.0/), which permits any noncommercial use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons license and indicate if changes were made.

Download article (PDF)

Volume Title
Proceedings of the Widyatama International Conference on Engineering 2024 (WICOENG 2024)
Series
Advances in Engineering Research
Publication Date
29 December 2024
ISBN
978-94-6463-618-5
ISSN
2352-5401
DOI
10.2991/978-94-6463-618-5_20How to use a DOI?
Copyright
© 2024 The Author(s)
Open Access
Open Access This chapter is licensed under the terms of the Creative Commons Attribution-NonCommercial 4.0 International License (http://creativecommons.org/licenses/by-nc/4.0/), which permits any noncommercial use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons license and indicate if changes were made.

Cite this article

TY  - CONF
AU  - Sabiqul C. R. Ramadhan
AU  - Verani Hartati
PY  - 2024
DA  - 2024/12/29
TI  - Identification of Standard Times to Determine Production Capacity: A Case Study
BT  - Proceedings of the Widyatama International Conference on Engineering 2024 (WICOENG 2024)
PB  - Atlantis Press
SP  - 184
EP  - 191
SN  - 2352-5401
UR  - https://doi.org/10.2991/978-94-6463-618-5_20
DO  - 10.2991/978-94-6463-618-5_20
ID  - Ramadhan2024