Schedule Management in Underground Municipal Pipe Network Construction Based on BIM Technology
Authors
Xiaohan Han, Jiayuan Wang, Miao Qun, Xiaotong Cui, Linlin Liu
Corresponding Author
Xiaohan Han
Available Online December 2016.
- DOI
- 10.2991/icseee-16.2016.42How to use a DOI?
- Keywords
- Building information modeling(BIM), Schedule management, Underground municipal pipe network.
- Abstract
According to the characteristics of the municipal pipe network, analyze the current status of the construction progress of the municipal pipe network and summarize the reasons for the low efficiency of the municipal. This paper puts forward the construction progress management method of the underground municipal pipe network, and takes the underground pipe network project of Qingdao Juxian Bridge Road section as an example to effectively improve the efficiency of the construction schedule management.
- Copyright
- © 2016, the Authors. Published by Atlantis Press.
- Open Access
- This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).
Cite this article
TY - CONF AU - Xiaohan Han AU - Jiayuan Wang AU - Miao Qun AU - Xiaotong Cui AU - Linlin Liu PY - 2016/12 DA - 2016/12 TI - Schedule Management in Underground Municipal Pipe Network Construction Based on BIM Technology BT - Proceedings of the 2016 5th International Conference on Sustainable Energy and Environment Engineering (ICSEEE 2016) PB - Atlantis Press SP - 228 EP - 231 SN - 2352-5401 UR - https://doi.org/10.2991/icseee-16.2016.42 DO - 10.2991/icseee-16.2016.42 ID - Han2016/12 ER -