Failure analysis of No.2 main transformer in Fushun SiShui substation
- DOI
- 10.2991/icmmct-17.2017.193How to use a DOI?
- Keywords
- transformer; outlet short circuit; turn-to-turn short circuit; short circuit current; three ratio method
- Abstract
the transformer is one of the most important equipment in power system, the maximum short current rated current is 25~30 times or more when an outlet short circuit occurs,short current will produce great mechanical force which is hundreds of times larger than the normal operation, Under the action of the huge short circuit electromagnetic force, many components such as the winding of the transformer may be damaged. This paper describes the whole process of of 2# main transformer in Fushun SiShui substation accident analysis, and the turn-to-turn short circuit accident of the winding is caused by interphase short circuit of the cable, this also provides a scientific basis for the transformer's fault detection.
- Copyright
- © 2017, the Authors. Published by Atlantis Press.
- Open Access
- This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).
Cite this article
TY - CONF AU - TianShu Hai AU - Xin Liu AU - ChengCheng Yue AU - Bo Li AU - Yan Liu AU - Jingzhong Li AU - Jie Sun AU - Yang Hu AU - Ying Li AU - Wenfeng Hao PY - 2017/04 DA - 2017/04 TI - Failure analysis of No.2 main transformer in Fushun SiShui substation BT - Proceedings of the 2017 5th International Conference on Machinery, Materials and Computing Technology (ICMMCT 2017) PB - Atlantis Press SP - 969 EP - 972 SN - 2352-5401 UR - https://doi.org/10.2991/icmmct-17.2017.193 DO - 10.2991/icmmct-17.2017.193 ID - Hai2017/04 ER -