Bearing Capacity Assessment and Maintenance Scheme Optimization on a 220kV Transmission Tower with Foundation Settlement

Authors
FengLi Yang, Chao Zhang, Binrong Zhu
Corresponding Author
FengLi Yang
Available Online November 2015.
DOI
10.2991/iccmcee-15.2015.75How to use a DOI?
Keywords
transmission tower; foundation settlement; stress ratio; assessment; staying wire.
Abstract

Finite element model of a 220kV transmission tower was established in general software ANSYS. The constrained method of the freedoms of tower foots with foundation settlements was proposed. According to the monitoring data of the non-uniform settlement, the relative settlement values were applied at the tower foots as displacement loads. By considering the relative position relationship between the wind direction and the settlement direction, the foundation settlement case can be combined with the design wind load case and the design ice load case, and structural analysis of the transmission tower totally includes 32 cases. The stresses of the main members and diagonal members at the tower head and tower body were calculated and assessed for different load cases. Optimization on the angle between staying wire and the ground was carried out. The reducing efficiency of stresses by using staying wires for two angles between the staying wires and the ground was compared.

Copyright
© 2015, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2015 4th International Conference on Computer, Mechatronics, Control and Electronic Engineering
Series
Advances in Engineering Research
Publication Date
November 2015
ISBN
978-94-6252-110-0
ISSN
2352-5401
DOI
10.2991/iccmcee-15.2015.75How to use a DOI?
Copyright
© 2015, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - FengLi Yang
AU  - Chao Zhang
AU  - Binrong Zhu
PY  - 2015/11
DA  - 2015/11
TI  - Bearing Capacity Assessment and Maintenance Scheme Optimization on a 220kV Transmission Tower with Foundation Settlement
BT  - Proceedings of the 2015 4th International Conference on Computer, Mechatronics, Control and Electronic Engineering
PB  - Atlantis Press
SP  - 384
EP  - 390
SN  - 2352-5401
UR  - https://doi.org/10.2991/iccmcee-15.2015.75
DO  - 10.2991/iccmcee-15.2015.75
ID  - Yang2015/11
ER  -