Bearing Capacity Assessment and Maintenance Scheme Optimization on a 220kV Transmission Tower with Foundation Settlement
- DOI
- 10.2991/iccmcee-15.2015.75How to use a DOI?
- Keywords
- transmission tower; foundation settlement; stress ratio; assessment; staying wire.
- Abstract
Finite element model of a 220kV transmission tower was established in general software ANSYS. The constrained method of the freedoms of tower foots with foundation settlements was proposed. According to the monitoring data of the non-uniform settlement, the relative settlement values were applied at the tower foots as displacement loads. By considering the relative position relationship between the wind direction and the settlement direction, the foundation settlement case can be combined with the design wind load case and the design ice load case, and structural analysis of the transmission tower totally includes 32 cases. The stresses of the main members and diagonal members at the tower head and tower body were calculated and assessed for different load cases. Optimization on the angle between staying wire and the ground was carried out. The reducing efficiency of stresses by using staying wires for two angles between the staying wires and the ground was compared.
- Copyright
- © 2015, the Authors. Published by Atlantis Press.
- Open Access
- This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).
Cite this article
TY - CONF AU - FengLi Yang AU - Chao Zhang AU - Binrong Zhu PY - 2015/11 DA - 2015/11 TI - Bearing Capacity Assessment and Maintenance Scheme Optimization on a 220kV Transmission Tower with Foundation Settlement BT - Proceedings of the 2015 4th International Conference on Computer, Mechatronics, Control and Electronic Engineering PB - Atlantis Press SP - 384 EP - 390 SN - 2352-5401 UR - https://doi.org/10.2991/iccmcee-15.2015.75 DO - 10.2991/iccmcee-15.2015.75 ID - Yang2015/11 ER -