Numerical Analysis of Influence of Large-Diameter EPB Shield Tunneling on Ground Deformation in Beijing Area

Authors
Tao Gong, Xiuren Yang, Chengzhi Qi, Deyun Ding
Corresponding Author
Tao Gong
Available Online September 2012.
DOI
10.2991/emeit.2012.186How to use a DOI?
Keywords
Large-diameter EPB shield, Tunneling, Three-dimensional finite element method, Ground deformation, Grouting pressure, Supporting pressure.
Abstract

A large-diameter earth pressure balanced (EPB) shield has been firstly used in the Beijing metro line 14 in China. In this paper, to take the experimental project of the metro line 14 as an engineering background, the tunneling process of the EPB shield with an outer diameter of 10 m was simulated using the three-dimensional finite element method. The numerical results show that the ground settlement mainly appears in three phases during the shield tunneling: before the arrival of shield, the arrival of shield and the grouting phase, and they take respectively 32%, 45% and 23% of the total settlement. During the backfill grouting, the soil deformation around the segments goes up in the normal direction of the segments with the increase of grouting pressure. However, as the grouting pressure decreases, the rebounding of ground deformation occurs. Only increasing the grouting pressure to control the ground deformation is not effective. The influence of supporting pressure in soil chamber on excavation soil disturbance is evident. When the supporting pressure is less than a half of earth press at rest, the excavation face may be not stable and collapse during the shield tunneling, however, when the supporting pressure is more than 2 times earth press at rest, the soil ahead of the shield cutter is obviously squeezed.

Copyright
© 2012, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2nd International Conference on Electronic & Mechanical Engineering and Information Technology (EMEIT 2012)
Series
Advances in Intelligent Systems Research
Publication Date
September 2012
ISBN
978-90-78677-60-4
ISSN
1951-6851
DOI
10.2991/emeit.2012.186How to use a DOI?
Copyright
© 2012, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Tao Gong
AU  - Xiuren Yang
AU  - Chengzhi Qi
AU  - Deyun Ding
PY  - 2012/09
DA  - 2012/09
TI  - Numerical Analysis of Influence of Large-Diameter EPB Shield Tunneling on Ground Deformation in Beijing Area
BT  - Proceedings of the 2nd International Conference on Electronic & Mechanical Engineering and Information Technology (EMEIT 2012)
PB  - Atlantis Press
SP  - 864
EP  - 869
SN  - 1951-6851
UR  - https://doi.org/10.2991/emeit.2012.186
DO  - 10.2991/emeit.2012.186
ID  - Gong2012/09
ER  -