Planning and Control of Projects with Different Types of Precedence Relationships and a Service Level Using Stochastic Simulation
- DOI
- 10.2991/cisia-15.2015.233How to use a DOI?
- Keywords
- Project Management; PERT; CPM; Project Simulation
- Abstract
We present a decision support system (DSS) to compute performance measures of a project under uncertainty on the activities’ duration as well as four different types of precedence relationships. The DSS generates replicates of the project’s performance, in which we simulate the duration of each activity. From these replicates, the expected completion time, the variance of completion time, the service time for a given service level and the probability that each activity will be in the critical path are estimated along with their corresponding measures of accuracy. A validation of the DSS was performed by computing the empirical coverage, mean and standard deviation of half-widths, mean square error and empirical bias for the main performance metrics of a given project. Our experimental results show that the procedures implemented in the DSS provide a good coverage and consistent half-widths.
- Copyright
- © 2015, the Authors. Published by Atlantis Press.
- Open Access
- This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).
Cite this article
TY - CONF AU - D.F Muñoz PY - 2015/06 DA - 2015/06 TI - Planning and Control of Projects with Different Types of Precedence Relationships and a Service Level Using Stochastic Simulation BT - Proceedings of the International Conference on Computer Information Systems and Industrial Applications PB - Atlantis Press SP - 869 EP - 872 SN - 2352-538X UR - https://doi.org/10.2991/cisia-15.2015.233 DO - 10.2991/cisia-15.2015.233 ID - Muñoz2015/06 ER -