Research on Synchronous Construction Control Technology for the Pylon and Girder of Maling River Cable-stayed Bridge

Authors
Shao-Hui Xiong, You-Jin Zhang
Corresponding Author
Shao-Hui Xiong
Available Online June 2016.
DOI
10.2991/ame-16.2016.129How to use a DOI?
Keywords
Cable-stayed Bridge, Synchronous Construction, Contrast Research, Feasibility, Construction Control.
Abstract

Pier No. 8 of Maling River Bridge was constructed by synchronous construction method of pylon and girder, while pier No. 9 was constructed by conventional construction method. In this paper, synchronous construction feasibility is analyzed theoretically by construction simulation computation based on the Maling River Bridge, and its construction control technology is stated.

Copyright
© 2016, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2nd Annual International Conference on Advanced Material Engineering (AME 2016)
Series
Advances in Engineering Research
Publication Date
June 2016
ISBN
978-94-6252-208-4
ISSN
2352-5401
DOI
10.2991/ame-16.2016.129How to use a DOI?
Copyright
© 2016, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Shao-Hui Xiong
AU  - You-Jin Zhang
PY  - 2016/06
DA  - 2016/06
TI  - Research on Synchronous Construction Control Technology for the Pylon and Girder of Maling River Cable-stayed Bridge
BT  - Proceedings of the 2nd Annual International Conference on Advanced Material Engineering (AME 2016)
PB  - Atlantis Press
SP  - 778
EP  - 790
SN  - 2352-5401
UR  - https://doi.org/10.2991/ame-16.2016.129
DO  - 10.2991/ame-16.2016.129
ID  - Xiong2016/06
ER  -