Stochastic Look-ahead Scheduling Method for Linear Construction Projects
Authors
Lingguang Song, Sang-Hoon Lee, Fitria H. Rachmat
Corresponding Author
Lingguang Song
Received 16 March 2012, Accepted 16 September 2012, Available Online 1 December 2012.
- DOI
- 10.2991/jrarc.2012.2.4.4How to use a DOI?
- Keywords
- linear construction projects, linear scheduling, simulation, pipeline construction.
- Abstract
Many construction projects involve repetitive operations that are exposed to various constraints and uncertainties.During construction field execution, schedulers must maintain and update look-ahead schedules, which coordinate work for the next several weeks based on the most recent productivity achieved. This study enhances the traditional linear scheduling method used for scheduling repetitive construction operations with stochastic simulation to incorporate uncertainty in activity performance during field operations. The proposed Stochastic Linear Scheduling Method (SLSM) was implemented and demonstrated in a pipeline construction project.
- Copyright
- © 2013, the Authors. Published by Atlantis Press.
- Open Access
- This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).
Cite this article
TY - JOUR AU - Lingguang Song AU - Sang-Hoon Lee AU - Fitria H. Rachmat PY - 2012 DA - 2012/12/01 TI - Stochastic Look-ahead Scheduling Method for Linear Construction Projects JO - Journal of Risk Analysis and Crisis Response SP - 252 EP - 260 VL - 2 IS - 4 SN - 2210-8505 UR - https://doi.org/10.2991/jrarc.2012.2.4.4 DO - 10.2991/jrarc.2012.2.4.4 ID - Song2012 ER -